2019

Commercial Operation: 1.32 MW solar project in Farmingville, Brookhaven, NY

April 2019

Commenced Construction: 3.58 MW solar projects in Shirley, Brookhaven, NY

April 2019

Mechanical Completion: 1.32 MW solar project in Farmingville, Brookhaven, NY

March 2019

2018

Commercial Operation: 3.02MW landfill project in Holbrook, Islip, NY

December 2018

Commercial Operation: 2.25MW landfill project in Hauppauge, Islip, NY

December 2018

Commenced Construction: 2.25MW landfill project in Hauppauge, Islip, NY

April 2018

2017

Commercial Operation: 1.75MW landfill project in Holtsville, NY

December 2017

Commercial Operation: 1.35MW landfill project in Manorville, NY

December 2017

Commenced Construction: 1.75MW landfill project in Holtsville, Brookhaven, NY

August 2017

Commenced Construction: 1.35MW landfill project in Manorville, Brookhaven, NY

August 2017

First engagement contracted as third party construction manager for another developer

April 2017

Sold 10MW portfolio of 9 projects developed by Agilitas at Notice to Proceed stage

April 2017

Commenced Construction: 650KW ground mount array in Rowley, MA

March 2017

Commenced Construction: 422KW ground mount system in Athol, MA

March 2017

Relocated and opened new headquarters location in Wakefield, MA

March 2017

Acquired at NTP stage: 422KW ground mount project in Athol, MA

March 2017

Acquired at NTP stage: 650KW ground mount project in Rowley, MA

February 2017

Acquired at mechanical completion stage: 496KW rooftop project in East Boston, MA

January 2017

Commenced Construction: 802KW project in Epping, NH

January 2017

2016

Established tax credit fund with 3 tax equity investors to facilitate the disbursement of tax credits, depreciation and cash flow valued at approximately $3M

Q4 2016

Commercial Operation: 57KW greenfield solar system in Keene, NH

December 2016

Completed Tax Equity Investment fund for NH projects

December 2016

Commenced Construction: 913 KW landfill project in Boxford, MA

October 2016

Commenced Construction: 993KW Milton NH Solar Farm

June 2016

Commenced Construction: 362KW Dover NH Solar Farm

June 2016